I have requested the remaining program dates from the Contractor completing the works around our school – SPA (Stabilised Pavements Australia). If weather permits please see below:

 

Road Works Schedule

09/02/2018

Trimming and Spray Sealing works at the Campbell St / Waugh St / Young St Intersection. Spray Sealing planned in afternoon.

10/02/2018

Planned Asphalt Placement to Young St and above Intersection adjacent to the School. Works completed on Saturday to take advantage of low traffic day due to non-school day.

12/02/2018 – 16/02/2018

Grader Trimming of road and final rolling works ready for seal – Waugh / Johnston/ Mackay / Cowdery Streets.

16/02/2018

Planned Spray Sealing Day for Waugh / Johnston/ Mackay Streets.

19/02/2018 – 20/02/2018

Grader Trimming of road and final rolling works ready for seal – Graham / Cowdery/ Webb Streets.

21/02/2018

Planned Spray Sealing Day for Graham / Cowdery / Webb Streets.

The spray seal planned will be the final coats of bitumen sealing for these roads – so a further follow up visit will not be required in this instance.

Final line marking works will not take place until approx. 4 weeks after final seal dates – to allow the bitumen seal to cure before lines are placed to ensure the longevity of the linemarking.